The original proposal
The council proposed 50 flats at 7–27 Albion Street. The planning committee later approved a scheme described as 15 social-rent homes and 35 open-market homes.
See the full source record →A complicated housing project reduced to the key public records. Read the sequence first. Open the evidence when you want the detail.
Southwick · Public-record timeline · Updated 16 September 2026
How to use this page: each card records a published event or statement. It does not assign technical or personal fault where the available evidence does not establish it.
The council proposed 50 flats at 7–27 Albion Street. The planning committee later approved a scheme described as 15 social-rent homes and 35 open-market homes.
See the full source record →With demolition under way, housing portfolio holder Carson Albury said he expected the new homes to be available very soon.
See the statement in context →Later records describe a 55-home affordable scheme and material planning changes. The eventual new-build project is repeatedly described by the council as 49 council homes.
Read the planning record →Westridge Construction entered administration with the homes unfinished. The council subsequently appointed Cheesmur to complete the development.
Read the council project record →Council photographs showed fitted kitchens and bathrooms. The council said the 49 homes were on track for completion in summer 2024.
See the council timeline →The council disclosed substantial remedial work and about £2.8 million of additional cost. It later attributed serious damp risks to poor design, workmanship and materials under the original contractor.
Read the committee record →Further council posts described kitchens, balconies and flats as nearing completion, with tenants expected before the end of the year.
See the council updates →The council reported further problems involving moisture pathways, sea-facing brickwork, balconies, insulation and cavity trays. Its report estimated £3.2 million of additional work and water-damage repairs to around half the flats.
Read the July 2026 report →The full investigation retains the detailed figures, source list, caveats and council records. The Evidence Trail is the quick route through the story, not a replacement for the underlying evidence.