Albion Street Southwick
Forty-nine council flats in Southwick remain unavailable to tenants more than five years after construction began, with Adur District Council now facing millions of pounds of further costs to make them habitable.
The Albion Street development was intended to provide 25 one-bedroom and 24 two-bedroom council homes for people on Adur’s housing waiting list.
Work started in March 2021.
The council says the scheme received a £2.4 million Homes England grant, with additional funding coming from developer contributions and Right to Buy receipts.
But the project has since passed through the collapse of its original contractor, the appointment of a replacement contractor, repeated delays, water penetration, construction defects and significant weatherproofing and design problems.
What the records show about the money
WATCH Sussex identified £9,184,951.94 in payments recorded to Westridge Construction in council spending data connected with the period in which the original contractor was delivering the scheme. That figure is a payment-data total and is not presented as the final reconciled construction cost of Albion Street.
After Westridge entered administration, Cheesmur Building Contractors was appointed to continue the project. Council contract records show a Cheesmur contract value of £1,739,438. Separate council approval included £994,411, followed by a further £1.1 million investment approved in 2025.
In July 2026 the council reported an estimated further £3.2 million requirement: £2.1 million for construction, £400,000 for professional costs and £700,000 in capitalised interest. The same report also referred to £1.3 million of prior-year expenditure including £698,000 capitalised interest. Those two interest figures may overlap and must not be added together without a reconciled ledger.
Reported complete, but still empty
Council planning and housing records reported the scheme as completed in 2025, while the homes remained unavailable for occupation. The July 2026 report says all 49 homes cannot currently be occupied and identifies water ingress in 25 of them.
Major remedial work is now required. The documented problems include water penetration, defects and weatherproofing/design issues. WATCH Sussex is continuing to seek the project records needed to establish the full chronology, responsibility for defects, recoveries and the final public cost.
Questions still requiring answers
The outstanding issues include the final reconciled cost of the development; how much of the original and replacement-contractor expenditure is attributable specifically to the 49-home scheme; the treatment of capitalised interest; whether the council will recover money through bonds, insurers, contractors or professional advisers; the effect on housing budgets; and the rent foregone while the homes remain unavailable.
WATCH Sussex has also sought the underlying contracts, spending records, defect and remediation evidence, revised programme information and lessons-learned material. Missing records are treated as unanswered questions, not evidence of wrongdoing.
Editorial status: this is the Albion Street investigation published by WATCH Sussex on 29 September 2026. The figures above retain the qualifications attached to the published investigation and should not be combined into a single project-cost figure unless the council provides a reconciled account.
49 empty council flats, millions spent and a £700,000 interest bill: what has gone wrong at Albion Street?
Five years after construction began on new council homes in Southwick, major rebuilding work is under way. Council records now raise questions about the cost of the development, almost £700,000 in capitalised interest and why it was reported as completed while the homes remained unoccupied.
Related fact check: Albion Street: what does “more than £3m” mean? Reviewed 3 September 2026. This does not close the investigation.
CURRENT POSITION
WATCH has reviewed the full 14 July 2026 officer report. It gives a £3.2m estimate of additional costs and proposes transfers from other housing budgets. The existing information request remains unanswered.
NEXT ACTION
Check the detailed committee resolutions, revised tenant-works programme, contracts, spending and recovery evidence, and the promised September lessons-learned report.
RESPONSIBLE BODY
Adur District Council
REFERENCE / TIMING
No authority reference recorded
No newly verified response date in this release; existing provisional dates are not presented as confirmed deadlines.
Status checked: 3 September 2026. An acknowledgement is not a substantive response. Research questions are not findings of wrongdoing.
Public sources
- Project page – funding, Westridge collapse, Cheesmur, 2024-26 updates — Adur & Worthing Councils
- July 2026 defects announcement – £3m+ initial estimate — Adur & Worthing Councils
- October 2025 decision – £1,112,967 additional budget — Open Council Network / council record
- Housing Delivery Test Action Plan 2024 – says completed March 2025/phased occupation underway — Adur & Worthing Councils
- 2021 planning consultation – material plan changes — West Sussex County Council
- Albion Street project page – design, planning and technical delivery for Adur — LRA Retinue Ltd
- Residential portfolio – Albion Street Clerk of Works; team Adur, RLF, Cheesmur — Beamore Management
- Westridge Construction insolvency record — Companies House
- 2024 South East awards project-team listing — LABC
- 7–9 Albion Street six-flat project details — Cityzen
- Albion Street Housing Scheme Update — JSC 14 July 2026 item 12, all 16 pages
- 17 July 2024 JSC — Albion Street JSC/17/24-25
- 23 October 2025 Council pack — JSC/58/25-26 decision reproduced pp21–22